| |
TUBLI WATER
POLLUTION CONTROL CENTRE, BAHRAIN
A major
wastewater treatment plant catering for the domestic and industrial wastewater
from the metropolitan areas
of Manama, Isa Town, and Muharraq, with a projected 2010 population of over
750,000. Phase I provides treatment
for a wastewater flow of 55,000 m3/day.
Four main
aeration tanks were implemented under Phase I. Four additional aeration tanks of
the same size and two
final clarifiers were added in Phase II to bring the total treatment plant
capacity to 230,000 m3/day and a B.O.D.
load of about 24,000 kg/day. The project also included the transmission,
distribution and storage systems to
irrigate 3000 Hectares of agricultural areas with treated sewage effluent.
The proposed
expansion has taken into consideration the excessive infiltration of ground
water into the sewerage system,
as well as the disposal of the septic sewage from existing septic tanks, which
imposed a high hydraulic flow and
extra B.O.D. load on Phase I of the Plant.
The services
included the following main tasks:
CONSULTING SERVICES :
The preparation of criteria,
process engineering, plans, specifications and tender documents for the issuance
on turnkey basis.
-
Bid evaluation and advice on
selection of contractors and equipment suppliers.
-
Review and approval of
detailed working drawings prepared by the construction contractors.
-
Construction supervision
including inspection and testing of machinery and equipment.
-
Supervision of operation and
maintenance of the completed Plant.
TUBLI
WATER POLLUTION CONTROL CENTRE - PHASE II, BAHRAIN
(PRODUCTION & UTILISATION OF TREATED SEWAGE EFFLUENT)
Expansion of a
major wastewater treatment plant catering for the domestic and industrial
wastewater from the metropolitan
areas of Manama, Isa Town, and Muharraq. Phase II provide Secondary and Tertiary
treatment expansion flow
of 230,000m3/day and transmission, distribution and storage systems to irrigate
3000 Hectares of agricultural
areas with treated sewage effluent.
The services
include the following main tasks:
-
Secondary
treatment expansion from 160,000m³/day to 230,000m³/day using
the low rate activated sludge
process, including the addition of
aerobic selectors, additional aeration tanks, clarifiers, thickeners and
sludge recycle facilities.
-
Upgrading of existing
facilities (inlet works, channels, substations) to accommodate the
expansion.
-
Repair works to existing
facilities and buildings.
-
New Sludge Dewatering and
Thermal Drying facilities for 38 ton / day of dried cake.
-
Primary treatment facility
for 4,000 m³/d of tankered wastes.
-
Odor Control facilities.
-
Upgrading and renovation
works to the existing Tertiary Treatment facilities and New Tertiary
Treatment facilities to treat a total
of 230,000m³/day. The New Tertiary Treatment facilities include fine
screens, secondary effluent lift station,
35,000m³ balancing tank, dual media filtration plant, ozone generation
facilities, ozone contact tanks, effluent storage
and transmission pumping station.
-
Transmission System
transmitting the 200,000m³/d of effluent to the Ag ricultural areas located
in the Northern, Central and Western
parts of the State of Bahrain.
-
Reservoirs and Pumping
Stations in each Agricultural area to
feed the distribution systems.
-
Distribution Systems for
irrigation of 2,500 Hectares of
Agricultural areas located in the Northern, Central and Western parts of the
State of Bahrain including telemetry
control.
-
Drainage System for the
Agricultural areas.
-
Complete instrumentation
system with central computer control,
including secondary treatment, thickeners,
sludge drying plant, balancing tanks, sand filters,
ozone disinfection's facility, effluent pumping stations,
substations, transmission distribution and storage
system.
-
Civil infrastructure
including roads, grading and drainage,
H.V. and L.V. electrical distribution, landscaping
and fencing.
-
Surge Analysis of the
complete system for initial and ultimate
conditions.
CONSULTING
SERVICES:
Criteria, process
engineering, architectural and engineering designs,
specifications, construction cost estimates and
tender documents.
SOLID
WASTE UTILIZATION FROM BAHRAIN TUBLI WPCC, BAHRAIN
A highly
mechanized form of sludge dewatering and drying treatment has been deemed
necessary due to the lack of
space in the facility to build additional drying beds. The Proposed sludge
dewatering and drying plant has been
designed to produce a product that is dries to 90% solids content and that is
fully disinfected. The bio-solids produced
are of a quality which enable the farmers to apply them on agricultural soils
without health hazards.
Sludge drying
beds have been used in Tubli to handle the produced sludge, the plant has 72
drying bed with a total capacity
of around 15 ton/day. The New Sludge Treatment plant will be able to handle a
design capacity (year 2010)
of around 38 ton/d.
After being
thickened, sludge is directed to the sludge drying plant, where firstly is
further dewatered. The principal components of the
sludge dewatering system are:
The second stage
of sludge treatment is thermal drying where the final product is in the form of
granules that can be used
as a soil conditioner. Sludge drying is the heart of the sludge handling process
and will be accomplished by the use of two
rotary thermal dryers. The heat source for the dryer is obtained from dual fuel
source burner using either
natural gas or diesel as a fuel source. The Sludge Treatment Plant will produce
a sludge that is dried to 90% solids
content and that is fully disinfected. This sludge can hence be directly applied
on agricultural areas. The
Thermal Drying process is designed as a closed loop system to minimize emissions
to atmosphere and facilitate
ordor control. The basic design concepts and parameters for the combined
dewatering and drying plant are as follows:
-
Biological
sludges from the return activated sludge channel of the extended aeration
process are drawn off and processed
in existing four thickeners. The thickened sludge is transferred to two
hopper bottomed, fully enclosed
balancing tanks located at the drying plant. Each balancing tank can provide
storage capacity for 3 hours
sludge production at the design rate of 38 tons dry solids (DS) per day at
2.5%dry solids. The tanks shall
be equipped with mechanical stirrers, and ventilation connections to the
odour control system.
-
The Sludge
dewatering and drying plant is designed to process the thickened sludge, at
a maximum rate of 38tons
of dr y solids/day with an average rate of 31.2 tons of dry solids/day and a
plant availability better than
85% . the dryer units are single pass without back mixing to ensure that no
dust is recycled to the front of
the dryer in order to eliminate completely any fire or explosion risks.
-
The dried
sludge is produced in a stable dust free palletised form with a dry solid
content in the range 89% - 92%
if the pelletising units are to be bypassed for any reason dryers will be
able to produce dry sludge in a dust
free granular form.
-
The product
conforms to USEPA class A criteria for pathogen reduction to enable
unrestricted distribution for
agricultural use. The maximum permissible pathogen levels for the product
are:-
-
Faecal coliform level <
1000/gram
-
Salmonella Sp. Bacteria <
3 MPN Per 4 grams DS
-
Helminth ova < 1 MPN Per 4
grams DS
REHABILITATION
& EXTENSION OF GREATER ANKARA WATER DISTRIBUTION SYSTEM, TURKEY
A
major scheme intended to upgrade and expand the water distribution network of
Greater Ankara (including suburbs)
spreading over 540 sq. km. with elevations from 780 to 1250 m.
With a present
population of 2.6 million, Greater Ankara is projected to have a population of
4.65 million by the year
2010.
The design work
for the upgraded and expanded scheme includes the following major elements:
-
1300
km primary distribution network (pipe diameters between 300 and 2200 mm),
-
6000 km secondary
distribution network (pipe diameters between 100 and 250 mm),
-
33 pumping stations with
single and multiple pump batteries,
-
63 storage reservoirs (1000
m3 to 30,000 m3 each),
-
Flow and pressure monitoring
installations;
-
Supervisory control and data
acquisition (SCADA) system; instrumentation and controls, and fire hydrants,
valves and appurtenances.
CONSULTING
SERVICES
The consulting
services for the project included studies and reviews of
existing conditions; establishment of present population and water demand;
future population distribution and projections; water demand
projections; sources capacity assessment; unaccounted-forwater surveys
and leakage prevention programs; hydraulic analysis of the
water networks and pumping or storage installations; hydraulic modeling
of the present and future systems; sensitivity and economic studies;
establishment of implementation programs; expenditure projections
and funding requirements; preparation of designs and tender
documents; assessment of and recommendations related to operation
and maintenance requirements, institutional set-ups and tariff
structures; and assistance to the authority in supervision of the construction.
MUSAFFAH-EAST
INFRASTRUCTURE, UNITED ARAB EMIRATES
The
Musaffah-East, Abu Dhabi, U.A.E. Water distribution, sewerage and drainage
project, commissioned by the Abu
Dhabi Municipality extends on a total of 3000 hectares.
It also includes
the Mafraq Industrial Area with an additional area of 1000 hectares. The network
is connected to a deep
interceptor collector up to 22 m in depth, 11 Km long with 4 pumping stations.
The main pumping station is 25
m deep with
a flow up to 3.5 m3 per second.
The project also
includes two pressure lines with a length of 9 Km each with 1300-mm diameter.
Construction requires 13
Km of micro-tunnelling with depths ranging from 13m to 20m.
The major
components of the project may be summarized as follows:
-
Water supply and irrigation
system including distribution lines down to 150mm diameter pipes,
reservoirs, pumping stations and chambers.
-
Surface water drainage
including subsidiary and trunk lines, pumping stations, detention basins,
outfall structures and other necessary work for satisfactory disposal of
surface water.
-
Sewerage facilities,
including house connections, subsidiary sewers and pumping facilities.
CONSULTANCY
SERVICES :
The Consulting
Services provided include:
-
Geotechnical Investigation,
-
Inception study,
-
Preliminary and Final
Designs,
-
Preparation of tender and
contract documents
-
Assistance in tendering,
-
Project Management and the
Supervision of construction works
METN EL
BAROUK WATER SUPPLY & WASTEWATER SCHEMES, LEBANON
Project
involved 230 kms of water and wastewater networks serving approximately 50 towns
and villages in the mountainous areas of North Metn,
Upper Metn, Barouk and Chouf districts.
Project key
elements involve :
-
Construction/ rehabilitation
of 32 concrete water reservoirs
-
Construction/ rehabilitation
of 87 km water transmission lines
-
Construction/ rehabilitation
of 130 km water distribution lines
-
Construction/ rehabilitation
of 12 km sewer lines
-
Submersible pump stations,
booster pump stations and five new chlorination stations.
-
The majority (85%) of the
project is financed by the World Bank, part of the National Emergency
Reconstruction
-
Programme (N.E.R.P.).
CONSULTING
SERVICES :
Feasibility and
economic studies, preliminary and detailed design, preparation of ten der
documents for project implementation and supervision of construction.

KESERWAN
REGION SANITARY SEWERAGE SCHEME, LEBANON
A major
scheme intended to provide master planning and implementation of a regional
sewerage scheme to
serve all the urban areas of Keserwan Region
extending over an area of 900 square kilometres and with a total projected
population of 670,000.
The scheme
provides sewerage, treatment and disposal of the wastewaters discharged by the
densely populated urban areas as well as the large
number of towns and villages within the project study area.
The main elements
of the project include;
-
Collector and trunk sewers
-
Pumping facilities and
pressure mains
-
Wastewater treatment plants
-
700 mm diameter sea outfall
with multiple diffusion nozzles
-
pre-treatment facilities
upstream of the sea outfall including screening, degritting, oil separation,
chlorination and pumping.
CONSULTING
SERVICES :
Feasibility and
economic studies, preliminary and detailed design and preparation of tender
documents for project implementation.
|