Planning, detailed design and construction
supervision for the Phase IV upgrade of the airport.
Improvements include a
new international terminal pier and domestic terminal; a new 9Mw power generation plant for
the island upon which the airport is situated, with a new 11kV ring main
power distribution scheme.
Additionally, air traffic management
systems have been upgraded, incorporating a new 33m high air traffic control
tower, Extended Communications and Surveillance facilities
such as VHF and MSSR housed in a new Air Traffic Services building.
Preparation of procedure for air traffic
control and the application thereof including staff training.